Fully sprint, Close the project in time
Our project people are working on the project closure at different cities of China from middle of November. Following with the working movement, the main projects are nearly to be closure and running.
No. 1 The wind, solar , diesel and energy storage DC micro grid system in Yecheng, Xinjiang
The 9 sets of our 20kW pitch controlled wind turbines are used for three army station in Xinjiang. They are all installed and operated from Dec 17th , to supply power the living and training of the barracks throughout the year
No.2 The wind and solar hybrid micro grid power supply project in Zhengzhou Airport
Technical feature of this project
- Support the IEC104 communication protocol, remote inspection, remote control
- Integrated controller and inverter machine, easy installation and maintenance
- Support the anti-countercurrent , realize the 100% usage for the power generated by the system
No. 3 The Laifushi marine ranch platform wind and solar power supply system
The wind turbine parts installation has been finished ; the system debug works is also nearly to complete, plan to run the system by this weekend
No.4 The Yangtze River Hydrological Monitoring Station wind and solar hybrid power supply project